Project Overview

Singapore’s First Commercial Liam-F1 Model R-1600 (5kW) Wind Turbine Installation at Infineon Singapore Cooling Towers

Reliance Green Energy PTE LTD successfully completed the installation of two Liam-F1 Model R-1600 (5kW) vertical-axis wind turbines at Infineon Singapore, with one turbine positioned near each of the facility’s two cooling towers.

This project demonstrates the use of cooling-tower airflow as an energy source, with specially designed wind deflectors directing the strong air draught generated by the cooling towers toward the Liam-F1 turbines. The project involved the complete process from wind turbine transportation and site preparation to mounting, electrical installation, commissioning, inspection and handover.

Two wind turbines installed at cooling towers of Infineon Singapore

Description of Liam-F1 wind turbines at Infineon
Project Highlights
  • ☞
    2 × Liam-F1 Model R-1600 (5kW) Wind Turbines: Installed at Infineon Singapore, with one turbine positioned near each cooling tower.
  • ☞
    Cooling Tower Airflow & Deflectors: Custom wind deflectors direct the strong air draught generated by the cooling towers toward the vertical-axis turbines.
  • ☞
    Robust Structural Foundations: Installed on concrete foundations measuring 1.2m × 1.2m × 0.6m supporting two-section hot-dipped galvanised mounting poles.
  • ☞
    Complete Electrical & Commissioning: Includes controller and inverter units installed in the pump room, full cable routing, main-circuit connection, final inspection and handover.
  • ☞
    High Wind Speed Resistance: Engineered with aerodynamic designs and structural bracing capable of withstanding severe tropical squalls and high wind gusts.
  • ☞
    Grid-Tied Power Benefits: Integrated with local grid standards so that any surplus clean energy generated is fed back into Singapore's electrical grid for commercial credits and financial returns.
  • ☞
    Zero-Emission Sustainability: Directly contributes to the client's corporate net-zero carbon goals by harnessing waste exhaust air to generate clean, renewable electricity.

Two Liam-F1 Wind Turbines at Infineon Singapore

Harnessing Cooling Tower Airflow for Renewable Energy

Two Liam-F1 Model R-1600 turbines were installed strategically near the cooling towers, with one turbine serving each cooling tower airflow area. The installation incorporates wind deflectors designed to guide and concentrate the cooling tower's strong air draught toward the turbine, helping the vertical-axis turbines capture the available airflow and convert it into rotational energy.

Cooling Tower Airflow → Wind Deflector → Liam-F1 Turbine → Generator → Electrical Energy

From Transportation to Installation

Step-by-Step Project Installation

Step 1 — Liam-F1 Turbine Transportation to Site

The Liam-F1 wind turbines and associated installation components were transported to the Infineon Singapore project site. The equipment was carefully prepared for site installation, including the turbine units, mounting structures, electrical components and supporting materials.

Step 1 — Liam-F1 Turbine Transportation to Site

Step 2 — Site Preparation & Mounting Foundation

The installation began with preparation of the mounting locations near the cooling towers. A dedicated concrete foundation was constructed to provide a stable and secure base for the wind turbine mounting poles.
Foundation Size: 1.2m × 1.2m × 0.6m

Step 2 Image 1
Step 2 Image 2

Step 3 — Concrete Foundation for Mounting Pole

The concrete foundation was designed to support the hot-dipped galvanised mounting structure and provide the required stability for the turbine installation. The foundation was completed and prepared for installation of the mounting pole.

Step 4 — Hot-Dipped Galvanised Mounting Pole

A two-section hot-dipped galvanised steel mounting pole was installed to support each Liam-F1 wind turbine. The galvanised construction provides a durable mounting structure suitable for the outdoor industrial environment.

Step 4 — Hot-Dipped Galvanised Mounting Pole

Step 5 — Installation of Wind Deflector

A specially positioned wind deflector was installed near the cooling tower to redirect the strong airflow generated by the air-conditioning cooling tower toward the Liam-F1 turbine. This component is an important part of the installation because it helps direct the available airflow toward the turbine.

Step 5 Wind Deflector Image 1
Step 5 Wind Deflector Image 2

Step 6 — Liam-F1 Turbine Mounting

The Liam-F1 Model R-1600 turbine was carefully positioned and secured onto the prepared mounting structure. The turbine was aligned with the airflow path created by the cooling tower and wind-deflector arrangement.

Step 6 Liam-F1 Turbine Mounting Photo

Step 7 — Two-Turbine Installation

Two Liam-F1 R-1600 turbines were installed, with one turbine positioned near each cooling tower. The completed arrangement allows each turbine to utilize the airflow available around its respective cooling tower.

Step 7 — Two-Turbine Installation

Electrical Installation

Connecting the Liam-F1 Wind Turbines

Once the mechanical installation was completed, the electrical works were carried out to connect the turbines to the project's electrical system:

Step 8 — Controller & Inverter Installation

Two wind turbine controller/inverter units were installed inside the pump room at Infineon Singapore. These units form part of the electrical control and power-conversion system for the Liam-F1 turbines.

Step 8 — Controller & Inverter Installation

Step 9 — AC Cable Installation

AC cables were laid for the three designated locations. The cables were routed through the prepared trunking system to provide the required electrical connections between the turbine system and the relevant electrical infrastructure.

Step 10 — Main Circuit Connection

Connection wiring completed to the main circuit. This stage connected the turbine system to the designated electrical infrastructure following completion of the cable installation.

Main circuit Installation Completed

Final Installation & Commissioning

Step 11 — Installation Completed

The installation works have been successfully completed. As part of the final project completion process, the Liam-F1 turbines, mounting structures, wind deflectors, controllers, inverters, and all electrical connections were thoroughly inspected and verified to ensure proper installation and operation.

Visual Showcase

Project Gallery

Transportation to Site
Mounting Foundation
Site Preparation
Galvanised Mounting Pole
Wind Deflector Setup
Wind Deflector Installed
Turbine Mounted
Two Turbine Installation
Controller Installation
Project Specifications
Project Infineon Singapore Cooling Towers
System Type Dual Vertical-Axis Wind Turbines with Wind Deflectors
Turbine Model 2 × Archimedes Liam-F1 Model R-1600 (5kW)
Application Cooling Tower Airflow Energy Recovery
Foundation Concrete foundations (1.2m × 1.2m × 0.6m)
Mounting Structure Two-section hot-dipped galvanised steel poles
Electrical System Controllers & inverters in pump room, trunking, AC cable routing, main circuit connection
Location Singapore
System Supplier Reliance Green Energy PTE LTD

A New Approach to Commercial Wind Energy

The Infineon Singapore project demonstrates how existing industrial airflow can be incorporated into a renewable-energy application. By positioning Liam-F1 turbines near cooling towers and using wind deflectors to direct the available airflow, the project provides a practical example of integrating vertical-axis wind technology into an existing commercial facility.

Reliance Green Energy PTE LTD continues to develop and implement renewable-energy solutions for commercial and industrial applications across Singapore.

Your Sustainable Tomorrow

Could Your Facility Recover Energy From Its Cooling Towers?

By partnering with Reliance Green Energy PTE LTD, you are choosing high-quality products, unparalleled local service, and a dedicated commitment to making your energy consumption cleaner, cheaper, and future-proof in Singapore.

We invite you to contact us today. Join the movement toward a more sustainable and energy-independent tomorrow. Our specialists are ready to provide a customized cooling tower wind energy assessment built for your business.

Request an Assessment

Use the channels below or visit our contact page to reach our team.

Phone Number
+65 9388 2202
Email Address
karlkoh1818@gmail.com
Showroom Location

7030 Ang Mo Kio Ave 5, #08-16 Northstar @AMK, Singapore 569880